A compelling certification highlights you. Attain the skills with the PRINCE2 Practitioner updated training questions at Prep4sureGuide: 266 practice questions for the PRINCE2-Practitioner exam.
| Certification Vendor: | AXELOS / PeopleCert |
|---|---|
| Exam Name: | PRINCE2 Practitioner Certification Exam (7th Edition) |
| Exam Number: | PRINCE2Practitioner |
| Exam Format: | Scenario-based objective testing, Open book (official PRINCE2 manual only), Multiple choice |
| Related Certifications: | PRINCE2 Foundation |
| Exam Duration: | 150 minutes |
| Real Exam Qty: | 70 |
| Exam Price: | USD 400–520 / GBP 470–520 |
| Certificate Validity Period: | 3 years |
| Passing Score: | 60% (42/70) |
| Available Languages: | Portuguese, German, Polish, English, French, Spanish |
| Recommended Training: | Official PRINCE2 Training |
| Exam Registration: | PeopleCert Official Registration |
| Sample Questions: | ![]() |
| Exam Way: | Online remote proctored or onsite test center |
| Pre Condition: | Hold valid PRINCE2 Foundation certification, or equivalent: PMP, CAPM, IPMA Levels A/B/C/D |
| Official Syllabus URL: | https://www.axelos.com/certifications/prince2/prince2-practitioner |
| Section | Weight | Objectives |
|---|---|---|
| PRINCE2 Processes | 30% | - Initiating a Project - Closing a Project - Directing a Project - Managing a Stage Boundary - Starting up a Project - Managing Product Delivery - Controlling a Stage |
| PRINCE2 Principles | 20% | - Manage by stages - Continued business justification - Focus on products - Learn from experience - Tailor to suit the project environment - Defined roles and responsibilities - Manage by exception |
| Tailoring PRINCE2 | 10% | - Tailoring principles, themes and processes - Adapting to project size, complexity and context |
| PRINCE2 Themes | 40% | - Risk - Progress - Quality - Plans - Organization - Business Case - Change |
The PRINCE2 Practitioner blueprint spans 4 domains — including PRINCE2 Processes (30%), PRINCE2 Principles (20%), PRINCE2 Themes (40%). The complete outline above lists every subtopic; work them from heaviest to lightest.
USD 400–520 / GBP 470–520 per attempt, 60% (42/70) to pass. Retakes cost the full fee — act now and prepare properly with the 266 practice questions for the PRINCE2-Practitioner exam at Prep4sureGuide.
Yes — download the free PRINCE2 Practitioner demo and preview the quality before paying. Purchases include 365 days of free updates by email; renew afterward at 50% off.
Hold valid PRINCE2 Foundation certification, or equivalent: PMP, CAPM, IPMA Levels A/B/C/D Eligibility rules change over time, so verify the current requirements on the official page (official PRINCE2-Practitioner exam page) before registering.
150 minutes for 70 questions. The Prep4sureGuide SOFT version — most proximate to the real exam in style and mode — builds the pacing you need on any Windows computer.
Through the vendor's official registration channels:
The PRINCE2 Practitioner is delivered Online remote proctored or onsite test center — pick the arrangement that suits you when booking.
Upon successful payment, our system emails the PRINCE2 Practitioner vce torrent automatically within about a minute — apply it on any computer with no limitation, with 24/7 help if nothing arrives within 2 hours. If you fail the corresponding PRINCE2-Practitioner exam within 60 days of purchase, we refund the full amount: send a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam, processed within 7 days. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products. Or exchange for two equal-value products free.
The PRINCE2 Practitioner is PRINCE2's certification exam for PRINCE2 Practitioner, at the Professional level. A compelling certification highlights you — from common to standout. Related credentials include PRINCE2 Foundation.
Yes:
After any course, sharpen up with the 266 practice questions for the PRINCE2 Practitioner — every answer expert-verified.
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
What products will be impacted by this change?
Correct Answer: A 🗳️
If the Project Board are too busy to authorize all change requests themselves, they can appoint?
Correct Answer: B 🗳️
Which of the following is False?
A Successful project management team should.
Correct Answer: C 🗳️
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
* Design for each month - correctly showing at public holidays and new company logo
* Selected photographs- 12 professionally-produced photographs, showing different members of staff
* Selected paper and selected envelope - for printing and mailing the calendar
* Chosen label design - a competition to design a label will be held as part of this project
* List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
* Create the customer fast using information from the Accounts and Marketing departments
* Confirm compliance with the Data Protection Legislation
* Create a design for each month - this will be done by the internal creative team
* Select and appoint a professional photographer
* Gather photograph design ideas from previous project and agree photographic session schedule
* Prepare a production cost forecast
* Select paper and envelope.
Stage 3 will include the activities to:
* Produce and select tie professionally-taken photographs
* Hold the label design competition and choose the label design
* Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
During stage 2, an early review of the photo design ideas from the Marketing department has highlighted the need for engineering machinery to be operating in the background during the photo sessions. This requires a change to the baselined Product Description for the photos. What action should the Project Manager take?
Correct Answer: C 🗳️
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
Checkpoint reports are being produced monthly. A week after the last checkpoint report was prepared, the team responsible for developing the 'classroom-based training materials' have realized that they will not be able to deliver the materials to the accreditor by the work package completion deadline.
Which action demonstrates application of the 'manage by exception' principle?
Correct Answer: D 🗳️
Explanation: Only visible for Prep4sureGuide members. You can sign-up / login (it's free).
Viewing page 1 out of 54 pages.
Viewing questions 1-5 out of 266 questions.
Over 37234+ Satisfied Customers
662 Customer ReviewsCustomers Feedback (* Some similar or old comments have been hidden.)Study material at Prep4sureGuide for the PRINCE2-Practitioner exam was very beneficial. Helped me score 94% in the exam. Very updated and detailed study guide. Suggested to all.
I passed my exam with 89% score last week. Anyone can attempt PRINCE2-Practitioner exam with this state of the art study guide provided by Prep4sureGuide, you will never regret.
I used Prep4sureGuide PRINCE2-Practitioner real exam questions to prepare my exam and passed PRINCE2-Practitioner with a high score.
The dump is helpful. With your PRINCE2 dump, I got my certification successfully last week! Thank u Prep4sureGuide!
Then one of my friends told me about Prep4sureGuide study guide and bring me to pass with this dump
I'm really glad on finding the all purpose Prep4sureGuide PRINCE2-Practitioner Study Guide to ace the exam. It imparted to me the best knowledge that led my way to success.
Undoubtedly, this PRINCE2-Practitioner training file is worth of its value! I passed the PRINCE2-Practitioner exam only with it. Thanks!
It was not an easy task without Prep4sureGuide to maintain such a high level of IT certification and passing PRINCE2-Practitioner exam with 85% marks. Thank you!
Good PRINCE2-Practitioner dumps! I will tell my friends if they want to apply for PRINCE2-Practitioner exam.
All credit goes to you guys for creating PRINCE2-Practitioner practice test for us. Thank you so much! It’s really a great opportunity to pass the exam!
Prep4sureGuide Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.
We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.
If you prepare for the exams using our Prep4sureGuide testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.
Prep4sureGuide offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.