NEW QUESTION # 10
In a existing project management project, all objects have been released and all subordinate tasks for the checklist items have been completed.
Why does the status change fail when you try to set the status of the checklist to Finish?
How can you trigger a workflow for a portfolio item?
- A. At least of the tasks has been configured
- B. The checklist item result is set to not ok
- C. A checklist item is still open
- D. You are missing the authorization for changing the project
Answer: B,D
NEW QUESTION # 11
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?
- A. Enable the split of financial values for the item type.
* Assign the item to two bucket of the classification hierarchy
* Maintain factors to split financial planning of the item - B. Enable financial planning for multiple buckets
* Assign additional buckets in financial planning
* Maintain factors to split financial planning of the item. - C. Enable the split of financial values for the item type
* Assign the item to two bucket of the portfolio
* Maintain factors to split financial planning of the item - D. Enable process change for multiple buckets.
* Start process change to reassign the item two buckets
* Maintain factors to split financial planning of the item
Answer: A
NEW QUESTION # 12
When you create an item from an initiative, which of the following objects are authorizations inherited from?
NOTE: There are 3 correct answers to this question
- A. Project management project
- B. initiative
- C. Parent bucket
- D. Project system project
- E. Portfolio
Answer: B,C,E
NEW QUESTION # 13
The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?
- A. The field service configuration of the item is missing
- B. The master switch for the interface settings for questionnaires it turned off
- C. The probability technical success field is configured as read only in the field control
- D. The field service configuration of the parent bucket of the item is missing
Answer: D
NEW QUESTION # 14
What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.
- A. Duration of tasks
- B. Relationships between tasks
- C. Role demands
- D. Project type
- E. Relationships between phases
Answer: A,B,E
NEW QUESTION # 15
In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question
- A. Project phase and WBS element
- B. Portfolio item and Project System project definition
- C. Project task and network activity
- D. Milestone task and WBS element
Answer: A,B
NEW QUESTION # 16
What is a prerequisite for using role charts in project management?
- A. A graphic profile is assigned to the role type
- B. The demand of a role must have been updated according to tasks
- C. The demand of a role must be distributed over a number of periods
- D. A graphic profile is assigned to the project type
Answer: C
NEW QUESTION # 17
Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?
- A. Cost Element
- B. Controlling Area
- C. Profit center
- D. CO Version
- E. Company code
Answer: A,B,D
NEW QUESTION # 18
How are groups linked to categories in capacity planning?
- A. A group is directly linked to one category
- B. A group is linked to multiple categories via view
- C. A group is directly linked to multiple category
- D. A group is linked to one category via view
Answer: A
NEW QUESTION # 19
What features does SAP analytics cloud deliver in combination with SAP PPM?
NOTE: There are 3 correct answers to this question.
- A. Provides models for financial and capacity planning
- B. Built-in connectors to data sources
- C. Intelligent algorithms highlighting possible data quality issues and distributing your data
- D. Out-of-the-box cost commitment reporting capabilities
- E. Smart transformations enabling you to quickly address and solve data quality issues
Answer: B,C,E
NEW QUESTION # 20
Which of the following can you use to create multiple portfolio items simultaneously?
- A. Primavera import
- B. Microsoft project import
- C. Microsoft Excel import
- D. Item template
Answer: D
NEW QUESTION # 21
Decision Flow management is delivered with standard scenarios.
For which combination of object types can you define a standard attitude synchronization?
- A. Portfolio item and WBS element
- B. Decision point and activity milestone
- C. Decision point and PS project definition
- D. Decision point and WBS element
Answer: D
NEW QUESTION # 22
How can an existing project management project be integrated with SAP controlling?
NOTE: There are 2 correct answers to this question.
- A. Assign the project roles to an existing internal order manually
- B. Transfer the project structure element to project system (PS)
- C. Transfer the project structure element internal orders
- D. Assign the project definition to an existing PS project definition manually
Answer: A,D
NEW QUESTION # 23
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required?
NOTE: There are 2 correct answers to this question.
- A. Categories
- B. Views
- C. Value types
- D. Cost element groups
Answer: A,B
NEW QUESTION # 24
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2 correct answers to this question
- A. Resource pool assignment is missing
- B. Assignment of resource management authorization object is missing
- C. Project response assignment
- D. Staffing manager assignment is missing
Answer: A,D
NEW QUESTION # 25
Where can you create a status for a what-if scenario in portfolio management/
- A. In the what-if scenario type
- B. In the review
- C. In the what-if scenario classification
- D. In customizing for the portfolio type
Answer: D
NEW QUESTION # 26
What is the PR/PLAN_INI_PREP report used for?
- A. To upload financial data from Microsoft Excel
- B. To transfer recoded time from CATS to PPM
- C. To transfer costs from accounting objects to PPM
- D. To create financial and capacity categories and groups based on customizing
Answer: D
NEW QUESTION # 27
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?
- A. Business Context Viewer (BCV)
- B. Evaluation
- C. Portfolio dashboard
- D. BI report
Answer: A
NEW QUESTION # 28
Which information can be assigned to a business partner in project management?
NOTE: There are 3 correct answers to this question
- A. Production resources or tools (PRT)
- B. SAP users
- C. Personal numbers
- D. Areas and locations
- E. Work centers
Answer: B,C,D
NEW QUESTION # 29
Which of the project definition in project management must be filled before you can release a project?
- A. Project type
- B. End date
- C. Controlling area
- D. Responsible
Answer: A
NEW QUESTION # 30
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question
- A. Project system project
- B. Initiatives
- C. Standalone items
- D. Project management projects
Answer: B,C
NEW QUESTION # 31
What can you with roles in project management?
NOTE: There are 3 correct answers to this question
- A. Define decision makers for an approval process
- B. Define authorizations for reporting
- C. Define responsibilities for structure element
- D. Define responsibilities for structure element
- E. Enable resource management
Answer: A,C,E
NEW QUESTION # 32
......
SAP C_S4PPM_2021 Certification Exam covers various topics related to SAP S/4HANA Portfolio and Project Management. These topics include project planning, execution and monitoring, resource management, portfolio management, financial management, and reporting. C-S4PPM-2021 exam also covers other related topics such as integration with other SAP modules, user interfaces, and project management methodologies.
C-S4PPM-2021 Exam Practice Materials Collection: https://www.prep4sureguide.com/C-S4PPM-2021-prep4sure-exam-guide.html
Get Latest and 100% Accurate C-S4PPM-2021 Exam Questions: https://drive.google.com/open?id=1LvbLa_5XN2ATPHmLx0eTyF41crHI7l6Y